[ Accessibility | Jump to content]

Offshore News

Offshore News

Here is the latest oil and gas offshore news for the UK Continental Shelf area. This page contains the latest information relating to offshore developments, obstructions and installation operations that are being undertaken by offshore oil and gas companies.

The information is displayed in chronological order, with the ability filter news by area or notice type. To filter news articles:

1. Select your working area (1-6) from the drop down box on the right.

2. Further filter the articles by selecting the 'news type' you're interested in from the drop down box to the right.

  Offshore news map

Refine Search

Filter options:
Area
News  

Seabed Activity - Drilling Operations   [Area One]

03 February 2012

Please note the following drilling operations which are currently scheduled to be undertaken.

  Development: 9/3b-7  
Drilling Rig(s) Anticipated Dates Installation Name Position(s) Vessel(s)
Start Date Finish Date
Rowan Norway 01-02-2012 15-08-2012 9/3b-7 a) 59° 56.061' N 001° 32.990' E
 

For further information, please contact: Gail Constable, ADTI, +44(0)1224 654400, gail.constable@deepwater.com

Seabed Activity - Drilling Operations   [Area One]

03 February 2012

Please note the following drilling operations which are currently scheduled to be undertaken.

  Development: Bluebell 15/24c  
Drilling Rig(s) Anticipated Dates Installation Name Position(s) Vessel(s)
Start Date Finish Date
Sedco 704 08-02-2012 08-03-2012 Bluebell 15/24c a) 58° 11.628' N 000° 47.762' E
 

For further information, please contact: Donald Murray, Premier Oil , +44(0)1224 615923, dmurray@premier-oil.com

Seabed Activity - Drilling Operations   [Area One]

03 February 2012

Please note the following drilling operations which are currently scheduled to be undertaken.

  Development: CASWI 14/19-D05  
Drilling Rig(s) Anticipated Dates Installation Name Position(s) Vessel(s)
Start Date Finish Date
Seawell 04-02-2012 03-03-2012 CASWI 14/19-D05 a) 58° 25.917' N 000° 15.533' W
 

For further information, please contact: Bert van Eyck, Talisman Energy UK Ltd, bvaneyck@talisman-energy.com

Seabed Activity - Construction/Installation Activities   [Area One]

03 February 2012

Please note the following construction activities which are currently scheduled to be undertaken.

  Development: Devenick Field  
Activity Type Anticipated Dates Installation Name Position(s) Vessel(s)
Start Date Finish Date
Monopile Installation 03-02-2012 12-02-2012 Devenick Manifold a) 59° 10.119' N 001° 35.918' E DSV Orelia
Rock Dumping 14-02-2012 Devenick S1 Well (9/24b-4) a) 58° 52.534' N 001° 31.526' E Nordness
Tie In Works 15-03-2012 31-03-2012 Devenick Manifold a) 59° 10.119' N 001° 35.918' E
Rock Dumping 25-02-2012 Devenick Manifold & East Brae a) 59° 10.119' N 001° 35.918' E Nordness
 

For further information, please contact: John Colegrave, BP E&P Ltd, +44(0)1224 851543, johnb.colegrave:uk.bp.com

Seabed Activity - Drilling Operations   [Area One]

02 February 2012

Please note the following drilling operations which are currently scheduled to be undertaken.

  Development: South Wood 22/18-06  
Drilling Rig(s) Anticipated Dates Installation Name Position(s) Vessel(s)
Start Date Finish Date
Seawell 31-01-2012 04-02-2012 South Wood 22/18-06 a) 57° 22.411' N 001° 27.206' E
 

For further information, please contact: Bert van Eyck, Talisman Energy UK Ltd, bvaneyck@talisman-energy.com

Deployment of Buoys - New Buoy   [Area Six]

02 February 2012

Please note a new buoy has been deployed at the following location.

  Buoy Type   Oceanographic Equipment Buoy
  Location   58° 25.203' N 006° 28.462' W
  Deployment Date   21-01-2012
  Recovery Date   31-01-2013

For further information, please contact: Arne Vogler, University of the Highlands, 01851 770 325, arne.vogler@lews.uhi.ac.uk

Anchor List   [Area One]

02 February 2012

Please note the following rig anchors that may extend up to one mile from the rig and may not always have buoys at their position. Fishing within the anchor pattern should be avoided. Fishermen may contact the installation or the ERRV (standby vessel) for positions of the anchors.

  Rig Name   Gryphon FPSO
Position
Anchor 1 - 59° 21.971' N 001° 35.103' E
Anchor 2 - 59° 21.456' N 001° 35.284' E
Anchor 3 - 59° 21.270' N 001° 35.109' E
Anchor 4 - 59° 21.022' N 001° 34.206' E
Anchor 5 - 59° 21.050' N 001° 33.804' E
Anchor 6 - 59° 21.411' N 001° 33.064' E
Anchor 7 - 59° 21.615' N 001° 32.992' E
Anchor 8 - 59° 22.087' N 001° 33.438' E
Anchor 9 - 59° 22.185' N 001° 33.795' E
Anchor 10 - 59° 22.114' N 001° 34.810' E
 

For further information, please contact: Robert Sinclair, GL Noble Denton, +44(0)1224 289182, robert.sinclair@nobledenton.com

Seismic Surveys   [Area Five]

02 February 2012

Please note the following survey activities which are currently scheduled to be undertaken.

Operator & Vessel Details Cable Length & Depth Survey Area UKCS Blocks Anticipated Dates Duration (Days)
Start Date Finish Date
Hydrocarbon Resources Ltd
Fugro Discovery
3EKE6
N/A
a) 54° 04.815' N 003° 43.059' W 113.27b , 110/2a 10-09-2011 31-03-2012 5
b) 54° 04.834' N 003° 39.758' W
c) 53° 57.065' N 003° 39.635' W
d) 53° 57.057' N 003° 41.081' W
e) 54° 03.258' N 003° 41.166' W
f) 54° 03.247' N 003° 43.032' W
 

Seismic Surveys   [Area Three]

02 February 2012

Please note the following survey activities which are currently scheduled to be undertaken.

Operator & Vessel Details Cable Length & Depth Survey Area UKCS Blocks Anticipated Dates Duration (Days)
Start Date Finish Date
Centrica Resources Ltd
Fugro Discovery
3EKE6
600m
3m
a) 53° 40.161' N 001° 18.072' E 48/12e 10-09-2011 31-03-2012 4
b) 53° 38.037' N 001° 23.325' E
c) 53° 35.809' N 001° 20.771' E
d) 53° 37.931' N 001° 15.521' E
Centrica Resources Ltd
Fugro Discovery
3EKE6
600m
3m
a) 54° 32.647' N 001° 22.062' E 48/12e 10-09-2011 31-03-2012 5
b) 54° 32.720' N 001° 27.625' E
c) 54° 30.025' N 001° 27.727' E
d) 54° 29.952' N 001° 22.170' E
Gardline Geosurvey Ltd
Ocean Researcher
GDLS
1300m
3m
a) 54° 13.594' N 000° 46.884' E 42/25, 43/21,22 29-01-2012 02-03-2012 6
b) 54° 19.541' N 000° 51.245' E 43/26,27,28
c) 54° 08.693' N 001° 33.726' E
d) 54° 02.775' N 001° 29.284' E
 

Seismic Surveys   [Area Two]

02 February 2012

Please note the following survey activities which are currently scheduled to be undertaken.

Operator & Vessel Details Cable Length & Depth Survey Area UKCS Blocks Anticipated Dates Duration (Days)
Start Date Finish Date
Nexen Petroleum U.K Ltd
Kopmmandor Stuart
MPOQH3
1200m
3m
a) 57° 55.543' N 001° 01.717' W 19/5a,10a 24-10-2011 30-04-2012 7
b) 57° 55.345' N 000° 49.570' W 20/1,6
c) 57° 48.883' N 000° 49.959' W
d) 57° 49.080' N 001° 02.070' W
Gardline GeoSurvey Ltd
Ocean Seeker
ZNZK5
1300m
3m
a) 57° 17.125' N 001° 28.146' E 22/23c 25-10-2011 29-02-2012 8
b) 57° 15.299' N 001° 33.558' E
c) 57° 12.065' N 001° 29.469' E
d) 57° 14.022' N 001° 24.103' E
Gardline Survey Ltd
Ocean Seeker
ZNZK5
1300m
3m
a) 56° 50.549' N 002° 04.959' E 30/1f & 30/1c 05-01-2012 15-03-2012 8
b) 56° 50.503' N 001° 59.060' E
c) 56° 53.736' N 001° 58.972' E
d) 56° 53.783' N 002° 04.880' E
Nexen Petroleum U.K Ltd
Fugro Discovery
3EKE6
1200m
3m
a) 57° 58.972' N 001° 12.563' W 19/4,5,9,10 15-01-2012 15-07-2012 15
b) 57° 55.955' N 001° 03.260' W
c) 57° 47.974' N 001° 12.398' W
d) 57° 50.980' N 001° 21.679' W
Shell UK Ltd
Fugro Discovery
3EKE6
N/A
a) 56° 51.865' N 001° 36.001' E 29/3a 01-02-2012 28-02-2012 .4
b) 56° 50.865' N 001° 35.713' E
c) 56° 51.305' N 001° 33.846' E
Valiant Petroleum Plc
Fairfield New Venture 
WERD
M/V C-Pacer
WDA4845 
300m
6-8m
a) 56° 46.059' N 001° 51.401' E 29/10,15, 30/6,7,8,11,12,13 01-02-2012 31-05-2012 50
b) 56° 46.251' N 002° 17.289' E
c) 56° 45.151' N 002° 17.310' E
d) 56° 45.193' N 002° 25.510' E
e) 56° 44.060' N 002° 25.527' E
f) 56° 44.068' N 002° 27.373' E
g) 56° 30.659' N 002° 27.565' E
h) 56° 30.493' N 002° 00.612' E
i) 56° 31.658' N 002° 00.581' E
j) 56° 31.584' N 001° 51.838' E